Introduction to Hydropower

Introduction to Hydropower

Hydropower is defined as a renewable energy source generated by the movement of flowing water on the surface of the Earth.This energy is produced repeatedly without altering the water’s physical properties. In a hydropower plant, water isdirected to move turbines, which in turn run electric generators. The potential energy of water stored in a dam is firstconverted into the kinetic energy of flowing water in the penstock, and then into electrical energy via the turbine–generatorcombination.

Power & Energy Conversion

The power output of a hydropower system can be calculated using the formula:

P = ρw × g × Q × H × n (Watts)

Energy is defined as the total power consumed over a period and is measured in kilowatt-hours (kWh). For instance,using 1 kW of power continuously for 1 hour consumes 1 kWh of energy.

Classification of Energy

Renewable Energy

Renewable energy sources are those that can be naturally replenished after use. They include:

Non-Renewable Energy

Non-renewable energy sources are transformed into unusable forms after consumption. Examples include:

Classification of Hydroelectric Plants

Based on Elevation Difference (Head)

Based on Installed Capacity

Hydropower Potential of Nepal

Nepal possesses tremendous hydropower potential due to its abundant water resources and dramatic topography. Key factors include:

Potential Estimates

Nepal’s hydropower potential can be categorized into three types:

Nepali Major River Basin Potential

River Basin Potential (MW)
Kosi 22,350
Gandaki 20,650
Karnali 32,010
Mahakali 4,160
Southern Rivers 4,110
Total 83,280

Classification Based on Operation

Classification Based on Storage capacity

Run-of-River Hydropower

In run-of-river plants, electricity is generated as and when water flows in the river. When the river dries up or the flow falls below a certain predetermined minimum (i.e. the minimum flow required for the turbine), electricity generation stops.

Due to the large variation in river flow in Nepal, these projects are normally designed for the dry season flows. They are suitable for perennial rivers that have adequate discharge throughout the year. The minimum dry flow must be sufficient to run the turbine efficiently and economically.

For example: Bhotekoshi Hydroelectric Plant (36 MW), Indrawati-III (7.5 MW), Modi Hydropower Plant (14 MW), etc.

Examples

  1. Kulekhani II: 2 × 16 MW, Francis Turbine, commissioned in 1986.
  2. Kulekhani III: 2 × 7 MW, Francis Turbine, commissioned in 2019.
  3. Upper Trishuli 3A Hydropower Station (60 MW): 2 units each of 30 MW; located in Rasuwa and Nuwakot districts; commissioned in 2019.
  4. Trishuli Hydropower Station (24 MW): 6 units each of 3.5 MW and 1 unit of 3 MW; commissioned in 196? AD; utilizing Francis Turbine.
  5. Devighat Hydropower Station (14.1 MW): 3 units; a cascade project of Trishuli Hydropower Station; commissioned in 1984 AD; using Vertical Francis Turbine.
  6. Gandak Hydropower Station (15 MW): 3 units each of 5 MW; using Kaplan Turbine Generators; located in Nawalparasi district; commissioned in 1979 AD.
  7. Modi Khola Hydro: 2 units each of 7.4 MW; located at Dimuwa in Parbat district.

Peaking Hydropower Projects of Nepal

  1. Kali Gandaki 'A' Hydropower Station (144 MW):
    • 3 units, each with a capacity of 48 MW
    • Located in Beltari, Syangja
    • Commissioned in 2002 AD
    • Operates with 6 hours of daily peaking
  2. Middle Marsyangdi Hydropower Station (70 MW):
    • 2 units, each with a capacity of 35 MW
    • Located in Lamjung
    • Commissioned in 2008 AD
    • Operates with 5 hours of daily peaking
  3. Marsyangdi Hydropower Station (69 MW):
    • 3 units, each with a capacity of 26 MW
    • Located at Aanbukhaireni, Tanahu District
    • Commissioned in 1989 AD
    • Operates with 4 hours of daily peaking
  4. Upper Tamakoshi Hydropower Station (456 MW):
    • 6 units, each with a capacity of 76 MW
    • Located in Dolakha District
    • Gross head: 822 m; Design discharge: 66 m³/s
    • Uses Pelton turbines
    • Operates with 4 hours of daily peaking
    • Live storage capacity: 1.2 million m³

Storage Type Hydropower

Storage plants have enough capacity to offset seasonal fluctuations in water flow and provide a constant supply of electricity throughout the year. Most rivers in Nepal show significant variations between the rainy (monsoon) season and the dry season. This variation often causes low power generation during the dry season when using run-of-river schemes.

To mitigate this, excess water during the rainy season is stored by constructing a dam and reservoir. This stored water can be used to generate electricity during the dry season (winter). Large dams can store several years’ worth of water and may be built in non-perennial rivers. In addition, the powerhouse may be located at the toe of the dam or separated from it.

For example: Kulekhani-I (60 MW) and Budhigand Hydroelectric Plant (650 MW) demonstrate the storage hydropower approach.

Kulekhani-I Hydropower Station (60 MW): Located in Makwanpur district, it features 2 units. The project uses a Rock Fill Earthen Dam with a height of 114 m and a total reservoir capacity of 85,300,000 m³, and is equipped with Pelton turbines.

Pump Storage Plants

Unlike conventional hydropower plants, pump storage plants reuse water. After water produces electricity by flowing through turbines, it is discharged into a lower reservoir located beneath the dam. During off-peak hours (when energy demand is low), some of this water is pumped into an upper reservoir. Later, during periods of peak demand, the stored water is released to generate additional electricity.

Pump storage plants generate power only during peak hours, providing extra capacity to meet high demand. However, these systems are comparatively expensive.

Methods of Fixing Installed Capacity of a Plant

  1. Marginal Cost and Benefit Approach:

    Total Marginal Cost = Annual cost of installed electromechanical equipment (AC) + additional costs (e.g., O&M costs).

    Marginal Benefit = Total energy generated × energy rate.

  2. Installed Capacity Optimization Approach:

    Determine the power corresponding to different percentage levels of time available discharge (from Q25 to Q75) and trade off between cost and revenue to achieve optimum benefit.

History of Power Sector Development in Nepal

Early Developments

Further Developments

History of Power Sector Development in Nepal

After 1990, the Government of Nepal recognized the drawbacks of a monopolistic power generation and distribution system. In response, it embraced liberalization by inviting the private sector to participate in power development through the Electricity Act 1992 and the Hydropower Development Policy 1992.

Achievements During the 9th Plan Period (1997/98–2002/03)

The 9th Plan Period proved to be a milestone in hydropower development, with both private and public sector initiatives making substantial progress:

The combined efforts resulted in an addition of 290 MW during this period, raising the total installed hydropower capacity to 537 MW. Overall, a progress rate of 46.2% was achieved, marking this period as one of the most successful eras for hydropower development in Nepal.

Planned and Proposed Hydropower Projects

Project Name Capacity
Upper Arun HEP 1061 MW
Uttar Ganga Storage HEP 828 MW
Dudkoshi Storage HEP 635 MW
Chainpur Seti HEP 210 MW
Aadhikhola Storage HEP 180 MW
Begnas Rupa Pump Storage HEP 150 MW
Upper Modi HEP 18.2 MW
Arun-4 HEP 490.2 MW
Total 3572.4 MW

Export of Hydropower

In an encouraging development, the Government of India (GoI) has granted concurrence for Nepal to export approximately 452 MW of power generated from various hydropower projects. The Nepal Electricity Authority (NEA) transmits this power via the Dhalkebar-Muzaffarpur 400 kV transmission line to the Day-Ahead Market of the Indian Energy Exchange (IEX), with an additional 40 MW supplied in real-time.

Hydropower Development Policy 1992 (Modified) 2001

In the wake of economic liberalization and open market reforms, the policies of 1992 were modified in 2001 to restructure the power system. These reforms addressed issues such as monopoly, transparency, cost, and electricity quality while ensuring that hydropower emerged as a key alternative to biomass and thermal plants.

Key Provisions

Licensing Framework

The licensing process within the policy is structured to facilitate hydropower projects of varying scales:

  1. Study/Survey License: For projects up to 10 MW, issued within 60 days of submission and valid for up to 5 years.
  2. Generation License:
    • For projects serving internal demand, the license is valid for 35 years.
    • For export-oriented projects, the license is valid for 30 years.
  3. Transmission and Distribution License: Issued for 25 years, with renewable extensions of 10 years at a time as per prevailing laws.
  4. For hydropower projects up to 1 MW, a formal license is not required; however, registration with the District Water Resources Committee is mandatory.

Investment and Power Purchase Agreements

Investment in hydropower initiatives may be executed through sole ventures or joint ventures involving both domestic and foreign investors. The associated Power Purchase Agreements (PPAs) outline tariff structures based on the project type:

Department of Electricity Development (DoED)

Initially established as the Electricity Development Center on July 16, 1993, under the Ministry of Water Resources, the organization was rebranded as the Department of Electricity Development in January 2000. The DoED is responsible for:

Water and Energy Commission Secretariat (WECS)

Established in 1975 under the Ministry of Energy, WECS functions as an advisory think tank to the government. Its primary objectives include:

Relevant Legislative Acts

Foreign Investment and Technology Transfer Act, 2049 (1992)

Water Resources Act, 2049

Electricity Act, 2049

Sediment Deposits in a Reservoir

Sediment deposition is a vital consideration for the design, operation, andmaintenance of reservoirs. Over time, sediments carried by inflowing water settle within the reservoir, reducing its effective storage capacity and potentially affecting operational efficiency.

Types of Loading

Sediment loading occurs in various forms, primarily characterized by the size and mode of transport of the sediment particles:

Factors Affecting Sedimentation

Several factors influence the rate and extent of sediment deposition in areservoir:

Sediment Control in Reservoirs

To mitigate the adverse effects of sediment deposition and extend thereservoir’s life, various control measures are implemented:

Life of a Reservoir

The useful life of a reservoir is largely determined by the rate of sedimentaccumulation. As sediments deposit over time, the effective storage capacitydiminishes, which may necessitate interventions such as dredging or othersediment management strategies to prolong the reservoir’s operational life.

Sediment Yield and Reservoir Trap Efficiency

Sediment Yield refers to the amount of sediment carriedby the inflowing water from the watershed, typically measured in tons peryear. The Trap Efficiency of a reservoir is the ratio ofthe sediment that the reservoir retains compared to the total sedimentinflow.

The following table summarizes these key parameters:

Parameter Description
Sediment Yield Quantity of sediment supplied by the catchment area (tons/year)
Trap Efficiency Percentage of incoming sediment that is retained within the reservoir

Capacity Inflow Ratio

The capacity inflow ratio is a critical metric for evaluating thesusceptibility of a reservoir to sedimentation. It is determined by comparingthe reservoir’s total storage capacity with the annual volume of water inflow.

Efficiency of Different Power Station

Power station

Efficiency

Steam Power station

25%

Hydro Power station

85%

Diesel Power station

35%

Nuclear Power station

55%

Hydropower Plant Components

This page presents the complete process of a hydropower project—from diverting the river water to the discharge back into the river. The diagram below shows the line components, and each component is explained with its functionality, premium features, common usage, and examples from Nepal.

Component Explanations

               ┌─────────────────────────────┐
               │        RIVER/STREAM         │
               └──────────────┬──────────────┘
                              │
                              ▼
               ┌─────────────────────────────┐
               │   Diversion Structure       │
               │ (Diverts water from natural │
               │      river course)          │
               └──────────────┬──────────────┘
                              │
                              ▼
               ┌─────────────────────────────┐
               │        Gravel Trap          │
               │ (Removes gravel and debris) │
               └──────────────┬──────────────┘
                              │
                              ▼
               ┌─────────────────────────────┐
               │          Intake             │
               │ (Collects & regulates water,│
               │  prevents debris entry)     │
               └──────────────┬──────────────┘
                              │
                              ▼
               ┌─────────────────────────────┐
               │      Settling Basin         │
               │ (Slows water for sediment   │
               │        settlement)          │
               └──────────────┬──────────────┘
                              │
                              ▼
               ┌─────────────────────────────┐
               │  Headrace Conveyance        │
               │ (Channels water to fore bay)│
               └──────────────┬──────────────┘
                              │
                              ▼
               ┌─────────────────────────────┐
               │          Fore Bay           │
               │(Acts as a small reservoir   │
               │ to ensure constant head)    │
               └──────────────┬──────────────┘
                              │
                              ▼
               ┌─────────────────────────────┐
               │ Surge Tank / Head Tank      │
               │ (Absorbs pressure surges;   │
               │   prevents water hammer)    │
               └──────────────┬──────────────┘
                              │
                              ▼
               ┌─────────────────────────────┐
               │         Penstock            │
               │ (Channels high-pressure     │
               │ water to the turbines)      │
               └──────────────┬──────────────┘
                              │
                              ▼
               ┌─────────────────────────────┐
               │Anchor Block / Support Piers │
               │(Stabilizes and anchors the  │
               │         penstock)           │
               └──────────────┬──────────────┘
                              │
                              ▼
               ┌─────────────────────────────┐
               │         Powerhouse          │
               │(Houses turbines & generators│
               │to convert water energy into │
               │       electricity)          │
               └──────────────┬──────────────┘
                              │
                              ▼
               ┌─────────────────────────────┐
               │          Tailrace           │
               │(Discharges water back to the│
               │      river/stream)          │
               └──────────────┬──────────────┘
                              │
                              ▼
               ┌─────────────────────────────┐
               │        RIVER/STREAM         │
               └─────────────────────────────┘

Diversion Structure

Function: Diverts water from the natural course of the river or stream, directing it toward the hydropower project’s intake.

Premium Uses: Some designs include adjustable gates, automated controls, and robust screenings to optimize water diversion.

Common Type & Nepal Example: Many run-of-the-river projects in Nepal employ simple yet efficient diversion weirs.

Gravel Trap

Function: Captures gravel and debris upstream of the intake to protect downstream structures.

Premium Uses: Self-cleaning gravel traps with automated controls are used in premium installations to reduce maintenance.

Common Use: Hydraulic projects with high sediment loads use gravel traps to prevent abrasion and clogging.

Intake

Function: Collects water from the diversion structure, regulates its flow, and prevents debris from entering the penstock.

Premium Uses: Modern intakes integrate trash racks and flow regulators with automated adjustment.

Common Use & Nepal Example: Various projects in Nepal incorporate sturdy intake structures to manage fluctuating river flows effectively.

Settling Basin

Function: Slows the water velocity so that sediment and heavy particles can settle at the bottom before being conveyed further.

Premium Uses: Optimally designed settling basins reduce the sediment entering turbines, thereby decreasing wear and tear.

Common Use: Both run-of-the-river and storage schemes use settling basins for sediment management.

Headrace Conveyance

Function: Transports water from the intake/settling basin to the fore bay. This may consist of an open channel or a pipe system.

Premium Uses: Engineered channels with flow control devices optimize energy efficiency and reduce water losses.

Common Use & Nepal Example: In Nepal, both open channels and underground penstock tunnels are used depending on the project’s scale and topography.

Fore Bay

Function: Acts as a small reservoir upstream of the powerhouse to regulate the water head and ensure a constant flow to the turbines.

Premium Uses: Advanced fore bay designs utilize automated level control to maintain optimal hydraulic head.

Common Use: Fore bays are essential where water supply and flow vary with time, ensuring steady operation.

Surge Tank / Head Tank

Function: Absorbs sudden pressure changes in the penstock (water hammer) to protect the downstream equipment.

Premium Uses: Surge tanks with automated pressure monitoring systems are used in higher-head plants.

Common Use & Nepal Example: Many high-head projects in Nepal include surge tanks to enhance operational safety.

Penstock

Function: Transfers water from the fore bay to the turbines with high pressure and velocity.

Premium Uses: High-performance steel penstocks, often welded and pre-stressed, minimize hydraulic losses.

Common Use & Nepal Example: Nepalese hydropower plants predominantly use well-engineered steel penstocks in both large and small installations.

Anchor Block / Support Piers

Function: Provides a stable foundation for the penstock, preventing movement or shifting due to external forces.

Premium Uses: Customized and robust anchor block arrays ensure maximum stability under varying site conditions.

Common Use: These structural supports are standard in all hydropower projects to secure the penstock.

Powerhouse

Function: Houses the turbine, generator, and other electrical equipment for converting water energy into electricity.

Premium Uses: Modern powerhouses incorporate advanced monitoring, control systems, and high-efficiency generators to optimize performance.

Common Use & Nepal Example: In Nepal, synchronous generators are widely adopted in powerhouses for their stable grid compatibility.

Tailrace

Function: Discharges water from the powerhouse back into the river or downstream watercourse, ensuring ecological balance while minimizing erosion.

Premium Uses: Tailrace channels in premium designs are engineered with erosion control measures and environmental considerations.

Common Use: Tailrace designs are tailored to local conditions; many Nepali projects utilize reinforced channels or lined conduits.

Headworks of Storage Plant

Components of a Typical Storage Plant

  1. Dam and Reservoir
  2. Spillway
  3. Trash Rack
  4. Surge Tank
  5. Penstock
  6. Turbine
  7. Powerhouse
  8. Draft Tube

Inside a Hydropower Plant

  1. Powerhouse
  2. Power Lines
  3. T t.nsfotmet (item unclear)
  4. Generator
  5. Control

Dam Components and Definitions

Purpose of Dam

A dam is generally most suitable in hilly areas where deep valleys offer extensive water storage. The stored water on its upstream side serves various purposes such as:

Types of Dam

A. Classification as per Function and Use

  1. Storage Dam: Normally constructed to store excess flood water for various purposes such as irrigation, water supply, and hydropower. It may be made of concrete, earth, or rockfill (e.g., Kulekhani-1).
  2. Detention Dam: Mainly constructed to control floods. A detention dam safeguards against possible flood damage on the downstream side. (No such dam in Nepal till date.)
  3. Diversion Dam: Used to divert river water into canals, conduits, or other streams. Typically a weir or low-level dam is constructed to raise the water level for diversion (e.g., Bheri-Babai Diversion, Sunkoshi Marine Diversion).
  4. Debris or Check Dam: A low-height dam constructed across a stream channel to conserve soil and retain sand, gravel, driftwood, or other debris.
  5. Coffer Dam: A temporary dam constructed to isolate the construction area from river flow during dam building.

B. Classification as per Hydraulic Design

  1. Overflow Dam: Built to allow the overflow of surplus water above its top. Only a few meters of its length act as the overflow section (e.g., Rigid Dam).
  2. Non-Overflow Dam: Designed so that water is not allowed to overtop the dam (e.g., Earth dam, rockfill dam, Kulekhani-1 dam).

C. Classification as per Structural Design

  1. Gravity Dam: A solid concrete or masonry dam that resists external forces through its own weight.
  2. Arch Dam: A curved masonry or concrete dam with the convex side facing upstream. It resists a major portion of water pressure through arch action and generally has less self-weight than a gravity dam.
  3. Buttress Dam: Consists of an upstream sloping deck supported by several buttresses or piers constructed of reinforced concrete and supported by struts or bracings.
  4. Embankment Dams: Constructed from locally available soils, gravel, and sand that resist external forces through their shear strength. They are usually trapezoidal in section (e.g., Earth dam, earth and rock fill dam).

D. Classification as per Material of Construction

Selection of Site for Dam

Design of Dam

Forces Acting on a Gravity Dam

Design of Earthen Dams

General Considerations

Earthen dams are typically more economical due to the use of local materials and unskilled labor. They can be constructed on relatively poor foundations with modern techniques like compaction, grouting, and foundation improvement. Continuous field observation and monitoring for deformation and pore water pressures are necessary during construction for any required modifications.

Demerits

Common Causes of Earthen Dam Failures

Design Criteria for Earthen Dams

Prevention of Seepage through the Embankment

Modes of Failure and Stability Analysis

  1. Overturning (Rotation) about the Toe: If the resultant of all the forces acting on a dam at any section passes outside the toe, the dam will tend to rotate and overturn about the toe. The ratio of the righting moments (anti-clockwise) to the overturning moments (clockwise) is called the factor of safety against overturning; a value generally greater than 1.5 is desirable.
  2. Compression or Crushing: A dam may fail when the compressive stresses exceed the allowable stresses of the construction material. The vertical stress distribution at the base is given by the equation:
    p = Direct Stress + Bending Stress.Masonry and concrete gravity dams are designed so that no tension develops; however, under severe loading conditions, a limited amount of tensile stress (around 5 MN/m2 under worst-case conditions) may be allowed. Tension cracks (for example, at the heel) may reduce the effective width of the base, shift the resultant force towards the toe, and lead to increased compressive stress and potential failure.
  3. Sliding (Shear Failure): Sliding occurs when the net horizontal force (external forces) exceeds the frictional resistance along any potential sliding plane at the dam or its base. The frictional resistance is given by the product of the normal force and the coefficient of friction. A factor of safety against sliding (F.S.S.) greater than unity is required.

Foundation Treatment for Gravity Dams

Preparing the Surface

The entire loose soil is removed until a sound bedrock is exposed. The final surface is then stepped to increase frictional resistance against sliding. In addition, a shear key might be provided.

Grouting the Foundation

Foundation grouting is divided into two parts:

  1. Consolidation Grouting: Shallow holes (called B holes) are drilled through the foundation rock, normally between 10 to 15 m deep and 5 to 20 m apart near the heel. A mixture of cement and water (grout) is forced into these holes at low pressure (about 30 to 40 N/cm2) prior to any concreting. This consolidates the foundation and later serves as a cutoff when high-pressure cement grouting is employed.
  2. Curtain Grouting: Curtain grouting helps in forming the principal barrier (or curtain) against seepage through the foundation, thereby reducing uplift pressures. To accomplish this high‐pressure grouting, relatively deeper holes (called “A holes”) are drilled near the heel of the dam. The spacing of these holes may vary from 1.2 to 1.5 m. Initially, holes are drilled and grouted at about 10 to 12 m apart, and then the intermediate holes are drilled and grouted.

    The depths of the holes vary from 30 to 40% of the total upstream water head for strong rock foundations, and may be as much as 70% of the water pressure head for poor rock conditions. After drilling, a mixture of cement and water (grout) is forced into the holes under high pressure. The grouting pressure is maintained as high as possible without lifting the foundation strata. Typically, the foundation pressure during high‐pressure grouting is approximately 2.5 D N/cm² (where D is the depth of grouting in metres below the surface).

    Grouting is generally performed in stages (approximately 15 m depth stages) and is carried out only after a portion of the dam section has been laid. This grouting may be accomplished from the foundation gallery, other galleries within the dam, from the upstream face if feasible, or in certain special cases, from tunnels driven into the foundation rock below the dam.

Seepage Control in Earth Dam

1. Providing the Drainage Filter (Filter Media)

To reduce downstream pore water pressure, a drainage filter is provided. This typically involves:

A multi-layer filter—commonly referred to as an inverted filter, horizontal blanket, or horizontal filter—is used in these applications.

2. Seepage Control Through the Foundation

Spillways: Design and Energy Dissipation

A spillway is a hydraulic structure designed to safely pass excess water when the reservoir is full. It is often regarded as a safety valve.

Types of Spillways

According to Hydraulic Regime:

According to Function/Purpose:

According to Regulation/Control:

According to Prominent Features:

Ogee Spillway

An ogee spillway is an improved form of a straight drop spillway where the downstream face of the weir is constructed to mimic the shape of the lower nappe of a freely falling water jet (an ogee shape based on projectile motion principles).

Shaft Spillway

(Also known as Morning Glory or Bell Mouth Spillway)

Side Channel Spillway

Straight Drop Spillway

Consists of a low-height weir wall with a downstream face that is roughly or perfectly vertical. To prevent scouring of the downstream bed from the falling water jet, an artificial pool with a concrete apron and a low secondary dam is constructed downstream.

Chute Spillway (Trough or Open Channel Spillway)

Siphon Spillway

Energy Dissipation

The energy dissipators for spillways can be grouped into several categories:

Hydraulic Jump Type Stilling Basin

A stilling basin is provided at the toe of a spillway to dissipate the energy of excess water by forming a hydraulic jump. As the flow moves at a critical depth over the spillway crest, it becomes supercritical at the dam toe and then meets subcritical flow downstream. The basin typically consists of:

Roller Bucket

A roller bucket dissipates energy when the tail water depth is much greater than the post-jump depth. When a high-velocity sheet of water slides down the spillway, it is arrested by the tail water.

Deflector / Flip / Ski Jump / Trajectory Bucket

This energy dissipator is used when the tail water depth is insufficient to form a hydraulic jump (i.e., when the tail water depth is much less than the post-jump depth). It is suitable for situations where the foundation rock is strong enough to withstand the erosive impact of the jet. The bucket deflects the high-velocity jet into the air so that it strikes the river bed at a considerable distance, where energy is dissipated through air resistance, viscous effects, and turbulence.

Selection of Energy Dissipators

Types of Stilling Basins

Gate Types and Location

Crest or Surface Type Gates

Deep Seated Gates

Headworks of Run-of-River (ROR) Plants

General Arrangement of Components

The headwork of a ROR plant extends from the weir/barrage to the settling basin. Its primary purpose is to withdraw the required amount of sediment‐free water from the river.

General Requirements of a Functional ROR Headwork

Intake

The intake is the hydraulic structure provided at the mouth (entrance) of a water conveyance system to withdraw water from the reservoir or river to the powerhouse.

Design Considerations

Points to be Considered

  1. Ensure minimum head loss as water enters the water conducting system from the reservoir (or pool behind a barrage).
  2. Prevent formation of vortices at the entry that could draw air into the system.
  3. Minimize the entry of sediment into the water conducting system.
  4. Prevent floating materials from entering the system.

Functions of Intakes

Location of Intake

The optimum location for an intake depends on several factors including dam type, reservoir geometry, the volume of water to be diverted, topography, submergence, geotechnical conditions, sediment exclusion, and ice control when necessary. It must satisfy the following primary considerations:

Types of Intakes Based on Plant Layout

A) Run-of-River (ROR) Type Plants

In ROR plants, water is drawn from a fresh, continuous river flow without appreciable pondage. Typical configurations include:

B) Reservoir Intakes

Design of the Intake Structure

  1. Selection of Intake Type: Based on site and hydraulic conditions, choose an appropriate type such as side, frontal, trench, pressure, or non-pressure intake.
  2. Determine Capacity: The design discharge should be 10–20% more than that of the turbine discharge.
  3. Fix the Intake Invert Level: Based on the sediment content (bed load) and design experience, the invert level should be set at about 0.5 m (or more) above the under-sluice level, as per site conditions.
  4. Satisfy Velocity Criteria:
    • The entrance velocity should be less than 0.6–0.8 m/s (up to 1 m/s for small systems).
    • Recommended criteria: Approach velocity = 1 m/s; Trash velocity = 0.6–0.75 m/s.
  5. Determine the Number of Openings: (Fast Track considerations may apply.)
  6. Account for Contraction Loss: Due to pier/abutment effects, the effective length is generally taken as 0.9–0.95 times the actual opening.
  7. Design the Intake Opening/Orifice:

    The opening is typically designed as a broad-crested weir operating under submerged or free-flow conditions, based on the upstream and downstream water levels. It can also be designed using the orifice flow equation:

    Q = C × A × √(2gH)

    Where:

    • H = River water level (depth in front of the intake)
    • h = Canal water level (depth in the canal)
    • C = Constant depending on the opening shape (0.6 for sharp-edged, roughly finished openings; 0.8 for carefully finished openings)
  8. Calculate Hydraulic Losses:
    • Trash rack loss
    • Entrance loss
    • Transition loss
    • Gate loss
  9. Ensure No Air Entrainment: Air may be drawn into the system due to vortex formation (from hydraulic jumps, high velocity, or submergence effects). This can be checked using the relation:
    s / (v × d) > C
    • s = Submergence (minimum of 0.3–0.5 m)
    • v = Velocity in the conduit
    • d = Diameter of the conduit
    • C = 0.3 (symmetric approach) or 0.4 (asymmetric approach)
  10. Provide Air Vents: To prevent cavitation, ensure that any entrapped air is vented properly.

Settling Basin (or Desander)

The main objective of a settling basin is to remove suspended particles of a particular size that can cause wear and tear on turbines and their accessories.

Classification of Settling Basins

a. Based on Flushing System

  1. Periodic Type
    Advantages: No loss of water.
    Disadvantages: Generation loss during flushing.
  2. Continuous Type
    Advantages: No generation loss.
    Disadvantages: Continuous loss of water during flushing.

b. Based on Prominent Feature

    1. Conventional Type

    • Sediment may be removed manually or with mechanical equipment after the basin is dewatered.
    • Deposited sediment may also be removed by lowering the water level inside the basin and generating a swift free surface gravity flow (i.e. conventional flushing system).
    • Two settling chambers are constructed for continuous operation.

    2. Hooper Type

    • This is a continuous flushing type wherein deposited sediment is removed continuously via a bottom opening.
    • Example: Sunkoshi (10 MW, information incomplete)

    3. Bieri Type

    • A developed form of the hopper type designed to control the loss of water during flushing.
    • It uses two horizontal shutters at the bottom – the lower one is fixed while the upper one moves horizontally.
    • When the sediment accumulation reaches a desired level, the upper shutter moves over the lower shutter and the sediment is flushed out. Finally, the shutter is reset to stop the flushing operation.
    • Example: Middle Marsyangdi (70 MW)

    4. Serpent Sediment Sluicing System (S4)

    • A developed form of the hopper type and Bieri type which addresses the major drawbacks:
      • Hopper type: Continuous loss of water.
      • Bieri type: Difficult operation of shutters.
    • It incorporates a float unit (the "serpent") which covers the flushing channel at the basin bottom when filled with water.
    • Once dewatered, the serpent becomes buoyant and flushes the sediment by opening the channel. When flushing is complete, the serpent fills with water, gradually sinks, and closes the channel.
    • The S4 system requires no machinery or energy input as it operates under gravity.
      Examples: Aandhikhola (5.1 MW), Khimti (60 MW), Jhimruk (12.5 MW)

    5. Split & Settle

    • Recognizes that sediment concentration is much higher near the bottom of the channel compared to the upper layer.
    • The dirtiest water (bottom layer) is diverted to a settling tunnel constructed parallel to the main conveyance.
    • The relatively cleaner water from the upper layer is conveyed to the powerhouse.
    • This concept saves the cost of a conventional settling basin and is especially useful when arranged underground.

    5. Hydrocyclone

    • Separates materials (sediments) that are denser than water using centrifugal force.
    • Sediment particles follow a helicoidal path toward an orifice, providing a longer effective settling length relative to the separator dimensions.
    • It typically removes particles ranging from 5 μm to 300 μm.
    • The unit consists of a conical-shaped vessel joined to a cylindrical section with a tangential feed inlet. An extended overflow pipe, known as a vortex finder, prevents short-circuiting of the feed.
    • A higher velocity flow is fed tangentially into the cylindrical section. This creates a forced vortex near the orifice and a free vortex in the outer periphery, building up a sediment concentration gradient across the vortex.

Professional Settling Basin Design Equations

1. Settling Velocity in the Laminar Regime (Stokes' Law)

For small, spherical particles in laminar flow (Re < 1), the settling velocity is given by:

$$v_s = \frac{g\,(\rho_p - \rho)d^2}{18\,\mu}$$

Alternatively, using the kinematic viscosity \( \nu = \mu/\rho \) and the relative density \( s = \rho_p/\rho \):

$$v_s = \frac{g\,(s - 1)d^2}{18\,\nu}$$

Definitions:

2. Settling Velocity in the Turbulent Regime

For larger particles where inertial effects dominate (typically at higher Reynolds numbers), the settling velocity is estimated by:

$$v_s = \frac{4\,g\,(\rho_p - \rho)d}{3\,C_d\,\rho}$$

Where \( C_d \) is the drag coefficient.

3. Particle Reynolds Number

$$Re = \frac{v_s\, d}{\nu}$$

4. Drag Coefficient (\(C_d\)) Correlations

The drag coefficient is expressed with the following empirical correlations:

5. Empirical Settling Velocity Formula

In practical designs, an empirical relationship (with \(v_s\) in cm/s and \(d\) in mm) is sometimes used:

$$v_s = a\,d^{0.5}$$

Where the coefficient \(a\) is determined by particle size:

6. Basin Flow and Dimensions (Continuity Equation)

Assuming steady, uniform flow in the settling basin:

$$Q = B\,h\,v$$

Solving for the basin width \(B\):

$$B = \frac{Q}{h \,v}$$

Where:

7. Sediment Load and Deposition

Sediment Load:

$$\text{Sediment Load (kg)} = Q\,T\,C$$

Where:

Volume of Sediment Deposit:

$$V_s = \frac{\text{Sediment Load}}{\rho_s\,F}$$

Deposition Depth (for a basin with plan area \(L \times B\)):

$$d_{dep} = \frac{V_s}{L\,B}$$

Inlet and Outlet Transition Guidelines

Hydraulic Tunnels

A hydraulic tunnel is an underground water conduit formed by excavation without disturbing the surface. Water can be conveyed through tunnels beneath high ground or mountains in rugged terrain where constructing a surface line is difficult.

Advantages

Disadvantages

Based on purpose or function, hydraulic tunnels may exist in the following forms:

Pressure and Non-Pressure Tunnels

Non-Pressure Tunnel: The tunnel in which the flow occurs as a free surface exposed to the atmosphere. The flow is open channel (e.g., spillway, diversion, tailrace tunnels).

Pressure Tunnel: The tunnel in which the flow occurs under pressure (e.g., headrace tunnel).

Hydraulic Design of Tunnels

Free Flow Tunnel (Non-pressure Tunnel)

The hydraulic design of a free flow tunnel is executed similar to that of a canal. Manning's frictional factors are used to compute the head loss along the tunnel length.

For example (approximate representation):

hf = (n² * v² * L)  

Pressure Flow Tunnel

The hydraulic design of a pressure flow tunnel is computed akin to pipe flow:

hf = (f · l · v²) / (2 · g · d)  

The head loss is computed using the Darcy–Weisbach friction factor. Discharge through a pressurized tunnel is calculated by the continuity equation (Q = A × v), where:

Based on sediment load considerations (suspended or bed load), a recommended velocity is about 2.5 m/s.

Size and Shape of Tunnel

The geometric design (shapes) of tunnels includes:

In cases where the rock is stratified, soft and closely laminated (e.g., sand, stones, silts, micaceous schists) and where high external pressure and tensile stresses exist, a sheared section may be considered:

Tunnel Alignment

After excavation, tunnel lining is applied to increase the hydraulic capacity, strength, and to reduce resistance and losses.

Advantages of Tunnel Lining

Tunneling Methods

  1. Heading and Benching
    • An old technique where only part of the tunnel cross-section (the heading) is excavated first and then enlarged to the required size.
    • Heading may be initiated at the top, middle, or bottom.
  2. Full Face Blasting
    • Entails uniform excavation of the entire tunnel section.
    • Suitable for tunnels passing through strong ground rocks.
  3. Tunnel Boring Machine (TBM)
    • Uses mechanical excavation for the full tunnel face.
    • Latest technology suitable for long tunnels and accessible sites (e.g., roads).
    • More expensive compared to other methods but offers fast, safe, and efficient construction in weak to moderate rock conditions.
  4. Drilling and Blasting

    (A method mentioned though detailed steps are not included.)

  5. Cut and Cover Method
    • The oldest tunneling method which involves digging a trench, constructing the tunnel, and then restoring the surface.
  6. New Austrian Tunnel Method (NATM)
    • A construction method and design philosophy that utilizes the strength of the surrounding soil to reinforce the tunnel structure.
    • Offers flexibility in design and excavation through ongoing monitoring.
    • Best suited for short-range (< 2 km) tunnels in regions with variable soil conditions.

Support in Tunnels

Tunnel support is required because the excavated rock tends to drop out of the roof. The time between blasting and the onset of roof collapse (without support) is known as the Bridge Action Period (ranging from minutes to weeks).

Size of Tunnel

Flow in Tunnels

Free Flow Tunnel

Manning's formula is used to calculate flow in a free flow tunnel:

Q = (1/n) * A * R^(2/3) * S^(1/2)  

Where:

Tunnel Lining

After excavation, tunnel lining is applied to increase hydraulic capacity, reduce resistance, enhance strength, and decrease losses.

Note: An empirical formula to calculate the thickness of the tunnel lining (in mm) is:

Thickness = 82 * D  

where D is the tunnel diameter in meters.

Main purposes of tunnel lining include:

Types of Tunnel Lining

  1. Shotcrete lining
  2. Precast concrete segment lining
  3. Cast-in-place concrete lining
  4. Steel liner plates
  5. Fiber-reinforced polymer (FRP) lining
  6. Brick or masonry lining
  7. Geotextile or geocomposite lining
  8. Tunnel lining with waterproofing membranes

Forebay (Head Pond) Design

A forebay (or head pond) is the upstream reservoir of a hydropower facility. It stores and regulates water before it is drawn into the pressure conduit (penstock) and subsequently to the turbine.

Estimation of Drawn Head

The drawn head is the effective vertical distance that water travels—from the forebay water level to the turbine's tailwater level—after deducting losses. It is estimated as:

Hd = Hf − Ht − Losses

Where Hf is the forebay water level, Ht is the tailwater level, and losses include friction and minor losses in the conveyance system.

Minimum Submergence Condition

To avoid cavitation at the turbine intake, a minimum water depth must cover the intake (i.e. a minimum submergence condition). Design guidelines usually specify a submergence ratio (for example, greater than 2.0) to ensure smooth flow without air entrainment.

Design of Surge Tank

A surge tank is a hydraulic structure placed between a slightly inclined pressure conduit (or tunnel) and a steeply sloping enstock (pressure shaft). It is designed to control hydraulic transients by acting as a water storage device or pressure neutralizer.

Functions of a Surge Tank

Design Conditions & Components

In designing a surge tank, engineers consider factors such as:

Design of Penstock Thickness

The penstock is the pressure conduit that delivers water from the forebay to the turbine. Its wall thickness must be adequate to withstand internal pressure, dynamic loads (such as those from water hammer), and environmental wear.

Basic Thickness Calculation

A commonly used design formula is:

t = (P × D) / (2 × σ × F)

In addition to static loads, dynamic effects from water hammer and allowances for corrosion are important considerations.

Hydraulic Transients (Water Hammer)

Water hammer is a sudden pressure surge resulting from the abrupt stoppage or change of flow in a pressurized pipe system. This phenomenon is typically caused by rapid valve closures or pump stoppages/failures.

Water Hammer Explained

When water flow is suddenly obstructed, the kinetic energy of the moving water is converted into a pressure pulse. This pulse can produce a loud "hammer knocking" noise as the water mass collides with the obstruction (such as a valve or pump) and the internal walls of the pipe.

Consequences of Water Hammer

Conditions That Cause Water Hammer

Water hammer often occurs during events such as:

Pressure Surge Calculation

The pressure surge from water hammer can be estimated by:

ΔP = ρ × a × ΔV

Hydro-mechanical Equipment

Hydraulic Turbines

A hydraulic turbine is a mechanical device that converts the potential energy contained in an elevated body of water (a stream or reservoir) into rotational mechanical energy. Its primary function is to drive an electric generator.

Types of Hydraulic Turbines

A) According to the Energy Conversion

Difference Between Impulse and Reaction Turbines

AspectImpulse TurbineReaction Turbine
Energy ConversionConverted into kinetic energy (KE) via the nozzlePartly transformed into KE before entering the runner
Pressure ChangePressure remains atmospheric throughout the runnerWater experiences changes in velocity and pressure within the runner
Water-Tight CaseNot required (runner not completely surrounded by water)Essential – the water completely fills the passages between the inlet and outlet, doing work on the blades
Draft TubeNot usedNecessary to recover lost kinetic energy
Flow RegulationBy means of a spear valve or a deflector fitted into the nozzleBy adjusting wicket gates (guide vanes)
Specific SpeedLow (7–20)Moderate to high (240–920) (Kaplan type)

B) According to the Direction of Flow

C) According to Name

Design parameters of Pelton wheel turbine:

1. Velocity of jet: At inlet \({V_1} = {C_V}\sqrt {2gH} \) where Cv = coefficient of velocity = 0.98 - 0.99.

2.Velocity of wheel: \(u = \phi \sqrt {2gH} \) where φis the speed ratio = 0.43 - 0.48.

3. Angle of deflection: 165 °unless mentioned.

4.Pitch or mean diameter: D can be expressed by \(u = \frac{{\pi DN}}{{60}}\)

5.Jet ratio: \(m = \frac{D}{d}\) (12 in most cases/calculate), d = nozzle diameter or jet diameter.

6.Number of buckets on a runner: \(Z = 15 + \frac{D}{{2d}}\) (Tygun formula) or,\(Z = 5.4\sqrt m \) , m = 6 to 35.

7.Number of Jets: obtained by dividing the total rate of flow through the turbine by the rate of flow through a single jet. The number of jets is not more than two for horizontal shaft turbines and is limited to six for vertical shaft turbines.

8. Size of bucket: length of bucket L = 2.5d, width of bucket B = 5d , depth of bucket Db = 0.8d.

Turbine Efficiency and Speeds

Turbine Efficiency

Hydraulic Efficiency: The ratio of the power developed by the runner to the net power supplied by the water at the turbine entrance.

Mechanical Efficiency: The ratio of the power available at the turbine shaft to the power developed by the runner (differs by the mechanical losses).

Volumetric Efficiency: The ratio of the quantity of water actually striking the runner to the quantity supplied. This accounts for water that may slip through without doing work.

Overall Efficiency: The ratio of the power available at the turbine shaft to the power supplied at the turbine entrance.

Turbine Speeds

  1. Runway Speed:

    If the external load on the machine suddenly drops to zero (sudden rejection) and the governing mechanism fails, the turbine races to the maximum possible speed known as the runway speed.

    Turbine Type Runaway Speed (% of Normal) Minimum Acceptable Head Variation (% of Design Head) Maximum Acceptable Head Variation (% of Design Head)
    Impulse 170–190 65 123
    Reaction (Data not clearly specified) 50 150
  2. Specific Speed (Ns):

    The specific speed of a turbine is defined as the speed of a geometrically similar turbine that would develop unit power under unit head conditions. (For example, the specific speeds for turbines developing 1 HP under 1 m head are approximately:)

    The specific speed of a turbine is in the range of

    Turbine

    Ns

    Pelton wheel

    10 - 60

    Francis

    60 - 300

    Kaplan

    > 300

  3. Synchronous Speed:

    When the turbine is directly connected to the generator, its speed must be synchronous. This is generally given by the equation:

    n = 120f / N

    where n is the turbine’s rotational speed (in rpm), f is the electrical frequency (in Hz, e.g., 50 Hz), and N is the number of generator poles.

  4. Speed Factor or Speed Ratio (φ):

    This is the ratio of the peripheral speed of the buckets or vanes at the nominal diameter to the theoretical velocity of water under the effective head acting on the turbine. In formula form:

    φ = (Peripheral Speed) / √(2gH)

The classification of the turbine based on the basis of operating head

Type of turbine

Operating head (m)

Pelton

300 m and above

Francis

60 m to 300 m

Kaplan

20 m to 60 m

Bulb

2 m to 20 m

Draft Tube

A draft tube is an integral part of low head turbines with large through flow (e.g., Francis and Kaplan turbines). It is an airtight diverging conduit whose cross-sectional area increases along its length, connecting the runner exit to the tail race level. Its primary functions include:

Criteria

Pelton Turbine

Francis Turbine

Kaplan turbine

Type

Pelton turbine is an impulse type water turbine

Francis turbine is an inward flow reaction turbine

Kaplan is a propeller-type reaction turbine

Head

It is used for high head ranging from 250 to 1000 m

It is used for medium head ranging from 40 to 600 m

It is used for low head ranging from 10 to 70 m

The direction of flow of water through blades

The flow of water is tangential to the runner. Hence it is also called as tangential flow impulse turbines

The flow of water through the blades combines both radial and axial flow.

The flow of water is axial through the blades

Discharge required

It required low discharge

It required medium discharge

It requires high discharge

Type of energy

It uses kinetic energy and converts into mechanical energy

It converts potential energy into mechanical energy

It uses both kinetic and potential energy and converts to mechanical energy

Efficiency

Its efficiency is about 85%

Its efficiency is about 90%

Its efficiency is about 90%

Governing of Hydraulic Turbines

Electro-mechanical Installation

Generator

An electric generator is a machine that converts mechanical energy into electrical energy. Usually, this energy is obtained from a rotating shaft (the armature). The generated electricity is used for power transmission at commercial, industrial, or domestic levels. In most systems, current is supplied at 50 Hz. A generator consists primarily of:

Hydropower Generator

The hydropower generator is the main equipment used to produce electric energy in a hydropower station. In a “water-to-wire” system, the turbine acts as the prime mover, converting the water power into mechanical energy which is then transformed into electrical power.

Types of Hydropower Generators

Types of Electrical Generators

Pump

A pump is a device that moves fluids—liquids or gases (or sometimes slurries)—by mechanical action. Pumps operate by mechanisms (typically reciprocating or rotary) and are used to perform mechanical work on a fluid.

Classification of Pumps

Component Parts of a Centrifugal Pump

A centrifugal pump typically consists of the following parts:

Reciprocating Pump

A reciprocating pump is a device that moves a fluid by displacing it with a piston or plunger executing a reciprocating motion in a closely fitting cylinder. The amount of liquid pumped equals the volume displaced by the piston.

Pumps designed with disk pistons can create pressures up to 25 bar, while plunger pumps can generate even higher pressures. The discharge rate from these pumps is almost entirely dependent on the pump speed.

The overall efficiency of a reciprocating pump is about 0 to 200% higher than that of a comparable centrifugal pump.

Although reciprocating pumps for industrial applications have become nearly obsolete due to their high capital and maintenance costs compared to centrifugal pumps, small reciprocating pumps (such as cycle pumps, football pumps, village well pumps, and pumps used as hydraulic jacks) still find wide application. This pump type is best suited for relatively small capacities and high heads and is very useful in oil drilling operations.

Main Components and Working of a Reciprocating Pump

The main parts of a reciprocating pump are:

Revision Notes Hydropower Engineering

Connect with Us

Follow us on social media to stay updated with the latest resources and news.